The Library Build

In 2017 Cathedral Primary School moved into the lower levels of Bristol Central Library. Below are some photos giving you an overview of the building process. 

To view the plans for the Library please click here.

 May 2017

Main Entrance

Work is continuing on the main entrance. The steps are now in place. These will lead into our lobby and the front desk.

 

Library

Parquet Flooring

Here is a section of one of the newly cleaned Parquet floors. They really are beautiful. This will give you an idea of how the old and new will be brought together throughout the school.

 

 

Library

Glass Walls and Doors

To let in as much light as possible throughout the school, there will be many glass walls and doors and being fitted. In this photo we are looking out of the Food Technology room towards an office space.

 

Library

In this photo we are looking into the Food Technology room.

 

Library

In this photo we have one of our classroom doors on the upper level, leading out into the hallway. Straight ahead you can see another classroom.

 

Library

Doors and Cupboards

Many of the doors, cupboards and worktops are now being fitted. In this photo we are looking at one half of the Food Technology room.

 

Library

The children's toilets are now fitted along with these really nice colourful doors.

 

Library

 

 April 2017

Main Entrance

The framework for the new entrance is now in place. The whole of this unit is being built on site, so we will keep you posted with photos as it develops.

 

The Library

The roof of the Main Entrance has a very unusual design with a crisscross effect. This means nothing can be fabricated off site.  

 

The Library

Steels Installed 

A crane was used to very carefully place the new steels. This was accurate work, making sure not to knock the walkway above (which belongs to the Central Library) or the chimney. 

 

The Library

Concrete Base 

Huge slabs of old concrete were dug up, then a metal frame was fitted and filled with a new layer of concrete. This will for the base of the new entrance.

 

The Library

 

 

 March 2017

Governor & Parent Tours

Over the last few weeks groups of parents have been able to visit the Library to see first hand the development of our new school building.

Here we have the Cathedral Primary School Governors all safely dressed up for their tour around the site conducted by Trevor Anderson the Project Manager.

 

Library

The Main Entrance

Work on the main entrance to school has now started. This whole section will all be built on site. Huge slaps of concrete are being dug up to prepare the ground and the building will feature and uniquely designed roof - we look forward to seeing it evolve over the next few weeks.


Library

Library

Staircase

The railing on the staircase have now been installed. And the space for the lift is now in place.


  

 February 2017

Staircase

The staircase is now being installed. This will take us up to the mezzanine level of the school. 

 

Library

Windows

The original panels have been put back in place. These windows divide one of the classrooms with the upper walk-way. The glass is going be replaced with safety regulation glass.  

 

Library

Walls

Rooms are really starting to take shape now. Many of the rooms even have an undercoat of paint on them which really brings them to life.

 

Library

 February 2017

Plumbing 

With rooms taking shape so is the plumbing! Here is one of the pupil toilets on the upper level of the school.

 

 

Library

Stonework

Specialist stonemasons have been working hard restoring sections of the stone throughout the school with fantastic results. 

 

Library

Ceilings and Floors

Things are starting to take shape now that the floors/ceilings are appearing. 

Here we have the upper level flooring looking towards the windows onto Deanery Road.

 


Library

This is the lower lever of the school looking in the same direction as the photo above.

 

Library

 January 2017

Ceilings and Floors

The metal work is now in place for the construction of the ceilings and floors in the what was the main hall area. This is very exciting as the rooms are now starting to take shape. 

 

Library

Library

 

 January 2017

Window Cleaning

Specialist cleaners have been working hard cleaning the stone around all of the windows in the new school. With a brush not much bigger than a toothbrush they have meticulously worked around each window bringing the stone back to life.

 

Library

 

 October 2016

CPS Staff visit the Library

Cathedral Primary School staff had the opportunity to visit the Library and see the changes that had been taking place. Everyone was supplied with the correct safety gear before entering the site and it was great to see that rooms within the building are now starting to take shape.

 

Library Visit

 29th September 2016

 

Metal Supports Now In Place

Metal supports are now in place for the floor that will be constructed in the main hall.

Supports are also in place for the removal of the wall in the hallway on the lower level.

 

Library

Library

The wall is now being removed in this upper level classroom really opening this space up.

 

Library

 12th September 2016

Building Work in Progress

Concrete arriving in large amounts to fill the hallway.

 

 

Library

While digging out the foundations in the hallway the builders came across a collection of bones and oyster shells. Building work stopped while Archaeologists were called in to verify what type of bones had been found. Luckily they were only animal bones and most likely food dropped by workers over 100 years ago. 

Library

Foundations being dug out in the hallway. The wall on the left will soon be removed. As the building was built on a slope digging out at one end turned out to be much deeper than the other. 

Library

A new window being installed into one of the classrooms on the lower level giving the room much more light.

Library

 10th June 2016

CPS Parents & Carers Library Visits

Today was the start of a week of visits to the Library made by our parents and carers.

With all the correct safety gear in place they were given a tour around the site by Project Manager Trevor Anderson and Quantity Surveyor Luke Brown. 

 

Library Updates

 

Getting the feel of the double height hall.

Library Updates

 

Trevor Anderson explaining the layout on the lower level.

Library Updates

 27th May 2016

Parquet Flooring

Here we see the Parquet flooring being carefully removed. They will then be replaced, sanded and polished at a later date.

 

Library Updates

Loo with a View

This is one of the two toilet rooms that are on the upper level of the new school. Due to the plumbing and water system these toilets are located at the front of the building with great views over College Square.

 

Library Updates

 

 5th May 2016

The School Hall

The metal shelving units have now all been removed, giving a better sense of scale for what will become our School Hall. As you can see from the size of the workman in the photo it is going to be a really impressive large room.

The lower photo is looking up towards the Hayward Lights and into the floor of the Central Library. This can also be seen in the top left corner of the photo above. There are 9 of these floor panels each containing 165 glass bricks - that's 1,485 glass bricks to clean, above and below, to let in as much light as possible.

 

Library

Library

 21st March 2016

Removal of the Floor

The flooring has now been removed to reveal what will be the new School Hall.

The removal of the floor to give a double height hall, is how Holden, the designer of the Library had originally intended this room to look. The Hayward Lights above this room will also draw more light into the Hall.

 

Library

Library

The Hayward Lights

The cleaning of the Hayward Lights is well under way bringing new light into the rooms below.

 

 

 

 

 

 

 

 

 

 

 

 

Library

 

Library

 21st March 2016

Cornelia Baltes visits the Library

Artist Cornelia Baltes (second from left) who will design the Public Art that will be displayed within our new building came to visit the School site. Also with her on this visit was Simon Morrisey (center) Public Art Curator, Claire Haley (second from right) Architect for Coda, Tracy Wylde (right) designer and Nigel Glastonbury (left) the site manager.

 

Library

Colour Combinations

The CPS team have had an interesting time looking at colour combinations for the interior of the new school. These are just some of the ideas and colour arrangements they looked at.

 

Library

 11th March 2016  

Uncovering the Hayward Lights

The screed over the Hayward lights is being removed with a sensitive chemical emulsion designed for heritage works.

Completion of this element is planned before the Library re-opens.

 Library Updates

Removal of the Newspaper Bins

The newspaper archive room is now clear following the removal of the shelving.

The shelving has been sensitively dismantled and will be reconstructed for sale as a reclamation item.

 Library Updates

Removal of library archive shelving

Dismantling of the archive shelving is progressing along with all existing mechanical and electrical services.

Temporary lighting has been installed and the area is being prepared to commence demolition.

 Library Updates

Let there be light!

Light is already streaming into the basement through the Hayward lights as they are being uncovered, unfortunately these will be covered over for fire protection during construction.

 Library Updates

 29th January 2016  

CPS Staff visit the Library

Cathedral Primary School Staff had the opportunity to go and visit the lower levels of the Library last week. It gave us a really good sense of what will be a fantastic new school, although we did have to use our imagination as certain walls will be taken down, and the shelving units are yet to leave the building. We all came away feeling really excited about the space we are going to moving into later in the year.

We will be going to visit the site again in a couple of months when the walls have come down and the shelving has been removed, so watch this page for photos from us.

Here, Miss Lloyd is showing us her new Year 2 classroom. The wall on the right is being removed to open up the space.

 

Library Updates

Miss Bailey, Miss Cameron and Miss Cummins looking at the view from the new Reception Class window.

 Library Updates

Many original features will be kept in our new school, such as items of furniture and these lovey sinks. 

 

Library Updates

Miss Cameron walking through the many shelving units that will soon be removed. The ceiling will also be removed here to give us the double height room which will become our main School Hall.

 

Library Updates

 15th January 2016  

Parquet floor protection works

The existing Parquet floor is being protected in readiness for the demolition of the shelving units, walls and floors.

The protection consists of 25mm Insulation, 9 to 18mm of Sterling board and 4mm thick flame retardant Corex sheet.

 Library Updates

Mechanical and Electrical Surveys

Our M&E Contractor Priddy Engineering are on site carrying out surveys of the existing services and planning for the alteration works, which keep some services required for the Library live through the School area.

 Library Updates

Library announces restricted opening period

The Library will be closed on weekdays for four weeks in March to make some improvements to the historic building and allow construction works to be carried out safely.

 Library Updates

Kier Site Management Team

Meet the Kier site management team, from the left Nigel Glastonbury (Site Manager), Simon Clark (Project Manager) and Luke Brown (Project Quantity Surveyor)

 Library Updates

 5th January 2016  

High Visibility Jackets

Kier Construction workers will soon be seen wearing these high visibility jackets. The jackets will have the CPS name and logo as well as the Kier name, making it clear who should be working on site.

 

Library Updates

Parquet floor damaged

Extensive damage to the original parquet floor has been uncovered upon removal of the base of the Library archive shelving.

It is proposed to leave the damage in situ in classroom areas for carpet to cover and refurbish in the Hall and corridor areas.

 Library Updates

Site set-up progressing

Site set-up is practically complete, with site office and canteen located in the Newspaper reading room and safety notice boards in the entrance lobby.

 Library Updates

Hoarding Installation progresses

The external site compound area hoarding is complete, with gated access for materials and removal of waste and notices for safety performance and visitor information.

 Library Updates

Structural Survey Issued

The results of extensive structural investigations into the existing building have been issued, the current design will need to be revised in some instances to suit the findings.

 Library Updates

 18th December 2015  

Listed Items removed for re-use

Internal screens and doors have been removed prior to the demolition works and are stored in the sub-basement car park for later refurbishment and building in to the new school. 

 

Library Updates

Protection works progressing

Existing features of the building have been protected with plywood in readiness for the demolition which commences in the New Year.

 Library Updates

Hoarding installation commences

The external site compound areas will have a 2.4m high timber hoarding around them, with gated access for materials and removal of waste.

 Library Updates

Holden Furniture stored

The Holden furniture which will be used within the completed school is safely stored in the sub-basement car park.

 Library Updates